Skip to content

City of Duluth Notebook, Monday

This specific work is described as a demonstration project, meant to be installed faster than a typical street project and at lower initial cost. Demonstration projects like this are meant to help prove a concept.

Table of Contents

Sign up for North Report

Portion of Skyline Parkway closed temporarily to allow for one-way traffic conversion work

Contractors performing the conversion of Skyline Parkway at the Enger Park Loop to one-way traffic begin work today. This section of Skyline Parkway will be closed temporarily to allow the contractor to complete the work quickly and safely. During the closure, Hank Jensen Drive will remain fully open to traffic and can be used as a detour. The closure is anticipated to last about a week, though the timeframe may need to be extended slightly.

This project will be the next step in the City of Duluth’s response to two fatal crashes in February 2024. This project will change this section of Skyline Parkway to a one-way section, with a delineated pedestrian area for use by pedestrians and bicyclists. Two marked pedestrian crosswalks will also be provided at trail crossings along the section. Among the most common concerns heard in the aftermath of those incidents was a concern regarding pedestrian safety along this specific stretch of road, vehicle speeds around a sharp curve near Twin Ponds, and cut-through traffic at a challenging intersection with 5th Street. In late 2024, the city closed the accesses to Fifth Street and Sixth Street due to the challenging intersection geometry, but was forced to delay implementation of the traffic flow conversion until this spring.

This specific work is described as a demonstration project, meant to be installed faster than a typical street project and at a lower initial cost. Demonstration projects like this are meant to help prove a concept; in this case, improving the safety for both motorized and non-motorized road users along a challenging corridor. At the same time, the demonstration project also gives the city flexibility to reverse course without significant expense if the anticipated safety and comfort benefits are not seen. Opportunities to provide feedback from road users of all types will be available shortly after the construction is complete; the city looks forward to feedback from all regarding this project.

Eklund Avenue reconstruction, Junction Avenue/Saint Marie Street rehabilitation project underway

Two significant road construction projects are set to begin today.

The Eklund Avenue reconstruction project includes full-depth reconstruction of Eklund Avenue, including bituminous pavement, concrete sidewalks, curb and gutter, driveway improvements, and utility work consisting of new water main and improved storm drainage system between Maple Grove Road and Swan Lake Road. The project is scheduled to be completed in late October. The affected section of the road will be closed to traffic during the work.

Also underway is the Junction Avenue/Saint Marie Street rehabilitation project. The project consists of a combination of street reconstruction and pavement rehabilitation along Junction Avenue and Saint Marie Street near the University of Minnesota Duluth campus between College Street and Carver Avenue. Project work includes full-depth pavement reconstruction, mill and overlay, concrete walks and driveways, concrete curb and gutter, and concrete ADA pedestrian ramps. Project utility work includes storm sewer replacement and rehabilitation, gate valve adjustments, manhole adjustments, and electrical duct bank installation. 

The Junction Avenue/Saint Marie Street rehabilitation project is scheduled to be substantially complete by mid-August of 2025.  Major work will be suspended from August 18, 2025, to September 8, 2025. Project completion is expected by late October 2025. Detours will be posted in the area.

Portion of N. Lake Avenue closed temporarily

Contractors working on the citywide lead water service replacement project closed the 600 block of North Lake today. This work is expected to take a week, with the road reopening to traffic on Friday, May 16. A signed detour will be posted redirecting traffic to First Avenue E. during the work.  

While a signed detour will be in place, drivers and commuters are encouraged to consider alternative routes to get to their destinations. Traffic delays should be anticipated.

-- City of Duluth press releases

Comments

Latest

Saturday Prep Sports Notebook

Benilde-St. Margaret’s broke open a tie match with three second-half goals to defeat Hermantown 4-2 in boys soccer Saturday. Henry Scroggins put the Red Knights on the board in the 21st minute, but Hermantown answered with two goals from Quinn Raukar — assisted by Hunter Nelson in the 25th and

Members Public
Howie: Chloe Johnson’s NIL payday awaits

Howie: Chloe Johnson’s NIL payday awaits

They’re already whispering about Chloe Johnson the way Minnesotans used to whisper about Gophers hockey legends who walked out of Iron Range barns like they owned the world. Only this isn’t the 1970s and Johnson isn’t some elitely-talented kid headed to a smoky college fieldhouse. She’s

Members Public
Howie: Fix the house, not the cabin

Howie: Fix the house, not the cabin

The numbers are stacked against the status quo, and the clock is ticking. In 2025, Duluth shoveled $1.2 million in tourism tax money into Spirit Mountain, propping up a ski hill meant to stand independently. That annual subsidy has turned into an open-ended drain, all while one of the

Members Public

Thursday Prep Scoreboard

Hermantown started its volleyball season with a straight-sets victory Thursday night, rolling past Duluth Marshall 25-17, 25-15, 25-23 in the Lake Superior Conference opener for both teams in Duluth. Setter Anna Bergerson handed out 16 assists to pace the Hawks’ attack. Outside hitter Lilah Conley finished with nine kills, 17

Members Public